Student Experience
Day 1: November 9th
Film Team: Script writing begins
Website Team: Planned the layout of the website
Kiosk Team: Started undoing last year's panels for this year. Many people were involved, as we needed lots of people to unscrew everything and install this year's panels. Also began the creative process to determine what to put inside the kiosk.
Day 2: November 16th
Film Team:Script complete. Started Casting.
Website Team: Going over rules. Ian K. and David learned how to use the camera to take pictures of the members. Writing and translation of game rules, penalties. Writing competition description, english and french. Creating and sending a team roster form
Kiosk Team: Continued installing panels and started to connect them
Day 3: November 23rd
Film Team: Props prepared
Website Team: Finding place for taking pictures. Setting up website and starting it. Set up game description page. Translation of game description page. Took 6 pictures
Kiosk Team: Continued connecting panels and started putting them up together into a structure.
Day 4: November 26th
Film Team: Permission granted to film in staff room.
Website Team: Basically finished both English and French versions of the game description page. Worked on the navigation bar. Started work on the team roster. Worked on the competition description page
Kiosk Team: Got all 9 panels up together.
Day 5: November 30th
Film Team: Scene 1 previsiaulized.
Website Team: Made more progress on the team roster. Created a google form to find out all the teams and their names. Editing the CRC robotics competition description font so all the pages look cohesive. Made robot progress and when we're going to do it
Kiosk Team: Installed overhead bars attaching the walls overhead to ensure they would be stable
Day 6: December 3rd
Film Team: Scene 1 filming.
Website Team: Finished the button to change the website language from English to French and vice versa. Made good progress on the team roster page. Added a Stocks page for the stocks minigame. Made good progress on the competition description page
Kiosk Team: Installed overhead bars attaching the walls overhead to ensure they would be stable
Day 7: December 7th
Film Team: Scene 1 filming. Scene 1 rough cut
Website Team: Tried many new ideas, some were used, like the marquee, and many other ideas were scrapped.
Kiosk Team: Applied first layer of primer to the walls.
Day 8: December 21st
Film Team: Closet scenes filming.
Website Team: Deciding colors for website, tried to make it visually appealing and added more information o competition description, as well as the home page.
Kiosk Team: Continued brainstorming on what to put inside the kiosk.
Day 9: January 11th
Film Team: Additional scenes filming.
Website Team: Took a lot of pictures. Added logos at top of pages. Tried to fix the home bar
Kiosk Team: Continued brainstorming on what to put inside the kiosk.
Day 10: January 14th
Film Team:
Final scene filmed.
Website Team: Figured out plan for home page. Edited and photoshopped photos and downloaded them. Added them to the website
Kiosk Team: Painted the first and second white layers onto the walls.
Day 11: January 18th
Film Team: Rough cut.
Website Team: Made very good progress with the home page and other pages.
Kiosk Team: Fixing bend in walls with double sided tape.
Day 12: January 25th
Film Team: Final cut and upload.
Website Team: Put on everyone's quote and pictures, working on minigames for stocks page and adding all team journals.
Kiosk Team: Removed overhead bar, switched one of the side panels out and started installing the piece to make the tv be able to attach to it. Also put tape on the walls in preparation of the painting of the stock graphs on the walls.
Day 13: January 28th
Website Team: Final touches, making sure there are no bugs, fixing mistakes and making sure that everything has been completed.
Kiosk Team: Finished installing the piece to attach the tv to the panel. Painted the stock graphs on 3 of the side walls.